Japan Nuclear Regulation Authority Says No to Fukushima Daiichi’s Ice Wall – FUKUSHIMA 311 WATCHDOGS – 11 février 2016

Japanese Nuclear Regulation Authority, the NRA, has put the kibosh on plans by Tokyo Electric Power Co. to start freezing underground soil at the crippled Fukushima No. 1 nuclear power plant–a stunningly expensive project intended to solve the crisis of accumulating radioactive groundwater at the site.

The installation of the equipment required for forming a wall of frozen soil at the Fukushima Daiichi nuclear power plant to prevent groundwater entering the reactor buildings has been completed. Approval from the Japanese regulator must be sought before the creation of the wall itself can begin.

Ice wall technology is already widely used in civil engineering projects, such as the construction of tunnels near waterways. Small-scale tests using the technology have already been completed at the Fukushima Daiichi site. However, the full-scale use of the technology at Fukushima will see the largest ground freezing operation in the world.

Installation of the equipment for forming the ice wall began in June 2014 and a test that has circulated the chilling liquid to specific parts of the wall has been under way since April 2015. The north, south and west sides of the facility were completed last September, while the remaining pipes on the east side facing the sea were placed within the ground in November.

Lire la suite…